Adaptation of Aleppo University Hospital

Yadan BiYad adaptation work in Aleppo

Adaptation of Aleppo University Hospital
Location: Aleppo University square, next to Aleppo University
Time span of adaptation: from 1 to 21 November
Initiation of adaptation work: 21/11/2014
Duration of adaptation work: 21 days
Criteria for site selection:
  • The Hospital serves a huge number of patients and PWDs with its multiple divisions.
  • Most of the PWDs are in the third floor, Physical Therapy division and in the seventh floor, neurological department. 
  • Three toilet rooms where adapted, one in the third floor and two in the seventh floor (men and women).
Types of adaptation work:
  • Lowering the bathroom floor level to commensurate with the out floor level.
  • Reconstructing the sewage network, electricity grid and the ceramics.
  • Installation the new adapted aluminum doors and windows.
  • Installation toilets and their restraints and sinks.  
Adapted place